INSPECTION AND TESTING OF EQUIPMENTS

Inspection and testing of the purchased equipment is one of the most important tasks in the engineering of a project. Its importance is sometimes underestimated. The first serious tests that the purchaser will witness are those in the factory where the equipment is assembled. These tests will also include a physical inspection of the equipment.

It is therefore important to state clearly in the specification what inspection and testing will be required and, where appropriate, what are the acceptable limits of the results. Most tests required in the oil industry are covered in international specifications and these can be used as references.

However, not all those in the reference documents need to be carried out in all cases. It is therefore prudent to state the requirements in the project specification in one or more of the following methods:

• Write a detailed description of exactly what is required, including the limits that are acceptable and the form in which the results should be reported. This method ensures a ‘self-contained’ approach that is very beneficial during the actual testing operation. Often time is limited to perform tests and to have all the requirements to hand without having to search through related documents enables the work to be completed very efficiently.

• Quote the exact clause numbers and sub-section headings in the reference documents for the particular tests to be performed. This may be less efficient when the time of the tests becomes due, especially if the reference documents are not easily to hand. If a statement is made such as ‘the switch gear shall be tested in accordance with the XYZ-123 international standard’ and no other clarification is included, then many debates can arise at the time of testing.

Whichever method is used it should be carefully checked by a quality assurance department before the specification is approved for purchasing the equipment.

Some types of equipment require ‘production tests’, ‘type tests’, ‘performance tests’, ‘routine tests’, ‘abbreviated tests’ or ‘special tests’, or a combination of these tests. The subtitles are sometimes used with different meanings. Production tests are required for complex equipment such as high voltage generators and motors, and these tests are performed in the factory before the complete unit is assembled. For example the rotors are balanced without the stator, air-to-water heat exchanges can be tested to withstand hydraulic pressure, winding insulation and individual coil insulation can be tested.

Type tests are performed on one from a group of identical units. These tests are comprehensive and some of which are usually only performed once in the life span of the equipment.

If the equipment is a standard product of the manufacturer for which existing certificates can show that a type test has previously been carried out, then the purchaser may wish to accept the certificate without repeating the test. This is largely a matter of choice than necessity.

Routine and abbreviated tests are generally the same form of tests. These are applied to those units in a group that have not been type tested. If only one unit is to be purchased and a type test has been waived then a routine test is usually performed and the results compared to those of a previous type test. The number of different tests included in the routine tests is less than that of the type tests.

Some of the tests may be identical in each category. Routine tests are usually witnessed by the owner or purchaser.

Performance tests are those tests that need to be carried out on combined equipment such as a gas-turbine driven generator or a pump driven by a high-voltage motor. In such cases the dynamic relationship between the various equipment's is of interest. For example, rotor vibration, critical speeds, run-up time to full speed, starting up and shutting down sequences, full-load and over-load performances, heat dissipation and cooling medium performance. Occasionally ‘special tests’ may be required. These may be due to the need to operate the unit in an unusual mode or to test special control systems that may involve associated equipment such as a power management system or a control panel. Special tests may be needed to verify the operation of protective devices in the equipment rather than the equipment itself, but which require the device to be in its fully functional position on its host equipment. The owner or the purchaser usually witnesses performance and special tests.

Routine tests usually include a thorough inspection of the equipment both before and after the testing is complete. Routine testing should not be confused with sample testing. For example a switchboard may consist of many panels of essentially the same type, e.g. motor starters, transformer feeders. The testing schedule should state whether samples of similar types could be tested in lieu of testing all the units. In either case a full routine test is generally required. Functional testing of mechanical operation should be applied to all the units, e.g. open and close contactors, rack in and out circuit breakers, operate switches and controls.

Comments

Popular posts from this blog

Auto Transformer Tap Changing

Auto Transformer Tap Changing: Working Principle, Switching Sequence and Applications Auto transformer tap changing is a practical method of adjusting transformer output voltage without unnecessarily interrupting the electrical supply. In power transmission and distribution networks, the load does not remain constant throughout the day. As load current changes, voltage drops across transformers, cables, feeders, and transmission lines also change. A tap-changing arrangement compensates for these variations by modifying the effective number of turns in the transformer winding. A reactor-type on-load tap changer uses a center-tapped reactor, selector switches, and a bypass or short-circuiting switch to transfer the load from one tap to the next. The reactor limits the circulating current during the transition, allowing the tap position to change while the transformer continues supplying the connected load. This article explains the auto transformer tap-changing working principle , switch...

PRIMARY SECONDARY AND TERTIARY FREQUENCY CONTROL IN POWER SYSTEMS

Primary, Secondary and Tertiary Frequency Control in Power Systems Author: Engr. Aneel Kumar Keywords: frequency control, primary frequency control, automatic generation control (AGC), tertiary control, load-frequency control, grid stability. Frequency control keeps the power grid stable by balancing generation and load. When generation and demand drift apart, system frequency moves away from its nominal value (50 or 60 Hz). Grids rely on three hierarchical control layers — Primary , Secondary (AGC), and Tertiary — to arrest frequency deviation, restore the set-point and optimize generation dispatch. Related: Power System Stability — causes & mitigation Overview of primary, secondary and tertiary frequency control in power systems. ⚡ Primary Frequency Control (Droop Control) Primary control is a fast, local response implemented by generator governors (dro...

Advantages of Per Unit System in Power System Analysis | Electrical Engineering

  Advantages of Per Unit System in Power System Analysis In electrical power engineering, the per unit (p.u.) system is one of the most widely used techniques for analyzing and modeling power systems. It is a method of expressing electrical quantities — such as voltage, current, power, and impedance — as fractions of chosen base values rather than their actual numerical magnitudes. This normalization technique provides a universal language for system calculations, minimizing errors, simplifying transformer modeling, and enabling consistency across multiple voltage levels. Because of these benefits, the per unit system is essential in fault analysis, load flow studies, transformer testing, and short-circuit calculations . ⚡ What is the Per Unit System? The per unit system is defined as: Q u a n t i t y ( p u ) = A c t u a l   V a l u e B a s e   V a l u e Quantity_{(pu)} = \dfrac{Actual \ Value}{Base \ Value} Q u an t i t y ( p u ) ​ = B a se   ...

Top 10 Transformer Manufacturers in the World

Top 10 Transformer Manufacturers in the World Transformers are among the most important and expensive assets in electrical generation, transmission, distribution, renewable-energy, industrial, infrastructure, and data-center projects. A power transformer changes voltage and current levels through electromagnetic induction while maintaining the system frequency. Generator step-up transformers increase generating-station voltage for efficient transmission, while grid and distribution transformers reduce voltage progressively before electricity reaches industrial, commercial, and residential consumers. The global transformer market continues to expand because of grid modernization, renewable-energy integration, industrial electrification, data-center development, replacement of aging equipment, and construction of new transmission infrastructure. One 2026 market assessment estimates that the global transformer market could grow from approximately USD 72.5 billion in 2026 to about USD 137....

Reversing the Direction of a Universal Motor: Methods and Circuit Diagram

How to Reverse the Direction of Rotation of a Universal Motor Introduction A universal motor is a high-speed electric motor that can operate on either an alternating-current or direct-current supply when designed for the applicable voltage and frequency. It is widely used in portable electric drills, grinders, vacuum cleaners, mixers, sewing machines, small machine tools, and other equipment requiring high starting torque and compact construction. The direction of rotation of a universal motor can be changed by reversing the direction of current through either the armature winding or the field winding relative to the other. The current must be reversed in only one of these windings. If the connections of both windings are reversed simultaneously, the relative direction of the field flux and armature current remains unchanged, and the motor continues rotating in the same direction. Before studying the reversing methods, readers may review the Universal Series Motors Electric Motors and...

Top 10 Power-System Protection Relays and Their Applications

A power system must continuously transport electrical energy while remaining within the thermal, mechanical, and insulation limits of generators, transformers, busbars, transmission lines, cables, motors, and switchgear. When a short circuit, insulation failure, overload, abnormal voltage, frequency disturbance, or equipment malfunction occurs, the affected section must be disconnected quickly. A delay of even a fraction of a second during a severe fault can increase equipment damage, expose personnel to danger, and threaten the stability of the wider electrical network. A protection relay monitors electrical quantities such as current, voltage, frequency, phase angle, impedance, power, and temperature. When measured values meet predefined operating criteria, the relay initiates an alarm, trips a circuit breaker, starts an automatic control action, or blocks an unsafe operation. The three basic duties of a protection relay are: Measure electrical quantities Detect abnormal or fault co...

MAIN AND PILOT EXCITER

Main Exciter The exciter (sometimes called the main exciter) is a synchronous generator that has its stator and rotor windings inverted. Its field winding is fixed in the stator, and the rotor carries the armature or AC . In addition the rotor carries the semiconductor bridge rectifier that converts the armature voltages to a two-wire DC voltage system. The AC voltages and currents in the armature are often alternating at a higher frequency than those in the main generator, e.g. 400 Hz. The higher frequency improves the speed of response of the exciter. The DC power circuit is coupled to the field of the main generator by the use of insulated conductors that pass coaxially inside the rotor of the exciter and the rotor of the main generator. This eliminates the use of slip rings, which were traditionally used before shaft mounted rectifiers were developed. A slight disadvantage of this technique is that the derivative feedback cannot be taken from the output of the exciter. Howeve...