Skip to main content

PLANNING AND OPERATING A RELIABLE AND ADEQUATE POWER SYSTEM

The electric utility industry over time developed planning, operating, and design standards to address customer expectations of reliable service. These standards were at first local in perspective but, as interties were built and the interdependent nature of the system became apparent, many of the standards were expanded to a regional and then a national perspective.

Transmission lines cannot be added helter-skelter based solely on the profits for the owner. Locations and designs for new substations selected by the distribution systems must recognize the future of the transmission system that will supply them. One cannot design a reliable low-cost automobile by having separate uncoordinated designs for the brakes, the transmission, the engine, and other essential systems. The same is true for the transmission system. It must be designed as an integrated whole.

Since the effects of electrical disturbances can spread over a wide, multistate region, the need for regional coordination in planning and operation is obvious. As the new market rules for the electric system are developed, the concern is that the rules in any one area do not lower the local reliability standards and thereby impact or impair the reliability of the grid.

Concurrently, over the last century and continuing to the present, customer expectations of reliable service have also increased. Outages which once were common place are now considered unacceptable. Momentary interruptions, which at one time were noticed by only a few customers, now impact many customers because of the widespread use of computers and other electronic devices.

Underlying the industry’s approach to reliability was the realization that its efforts should be multidimensional:
  • Plan the system to have enough generation, transmission, and distribution capacity
  • Design the system to reduce the probability of equipment failure
  • Operate the system to remain within safe operating margins
  • Be prepared to restore the system quickly, in the event of a supply disruption in all cases, the industry’s efforts involve a trade-off between reliability and costs.
It would be impossible to build enough facilities or operate with enough of a reserve margin to have a perfectly reliable system. For example, some types of common-mode failures due to causes such as tornadoes, ice storms, or hurricanes involve so many facilities that it would be financially impossible to design a system to tolerate them. This is why the requirement for restoration plans is so important. These plans should encompass a wide range of issues including, but not limited to clear lines of authority for managing the restoration process, staff mobilization plans, plans to rapidly acquire and deliver spare parts to replace damaged equipment, order of restoring generation and transmission facilities, and so on. The basis for the standards that have been developed are varied.

All reflect, in one way or another, a view of an acceptable level of reliability. Generation planning standards have, in the past, been tied to a statistical measure. Standards for operating the generation and transmission systems are based primarily on the collective judgments of utility personnel. Over the years, these standards have been accepted and legitimized by local, state, and national regulators in rate cases and in after-the-fact reviews of outages. In many of these reviews, customer complaints over service reliability and over costs have caused modifications to aspects of individual standards. For example, problems with restoration times in some areas after major storms have led to requirements for detailed and publicized restoration plans reflecting customer inputs.

Attempts have been made to determine and set the level of transmission system reliability based on the reliability of each of the components of the system. Although appealing in theory, this effort flounders on the magnitude and variations in equipment that constitute a power system. The system is designed to reflect good engineering judgment. For example, an engineer can select a number of designs for a new bulk power substation depending on its criticality. The planner could select a substation with a breaker-and-a-half arrangement, which provides more redundancy and, hence, a higher level of reliability than a ring bus design provides.

Some specific examples of major blackouts from which lessons have been learned are listed below. This is by no means a comprehensive list but it does illustrate that large-scale blackouts are not uncommon.
  1. 1965 in Northeast United States
  2. 1967 in Mid-Atlantic United States
  3. 1977 in New York City
  4. 1978 in France
  5. 1987 in Tokyo
  6. 1997 in California
  7. 1997 in New Zealand
  8. 2003 in Northeast United States122
  9. 2003 in London
  10. 2003 in Denmark/Sweden
  11. 2003 in Italy
  12. 2004 in Greece
  13. 2005 in Australia
  14. 2005 in Moscow
  15. 2006 in Europe
  16. 2006 in Tokyo
  17. 2007 in Victoria, Australia
  18. 2007 in South Africa
  19. 2007 in Colombia
  20. 2008 in Brazil
Reliability will depend on whether the “Three Musketeers” or the “Lone Ranger” approach is used. With the Three Musketeers approach, problems of one system or company are shared by all in an effort to minimize total societal costs. In the Lone Ranger approach, each system or business customers suffers alone the consequences of its problems. Some believe this will provide motivation for all to meet their obligations.

One finds in the literature discussions of the customer’s willingness to pay for a greater level of reliability. There are two ways to give greater levels of service:
  1. Provide more redundancy of supply to one customer than to another
  2. In the event of a disturbance or insufficient capacity, disconnect or interrupt the customer who does not pay a premium rate for electricity
Given the reality of how a power system is physically structured, the redundancy option has limited application in protecting specific customers against transmission facility outages, especially when the exposure is to a security violation, that is, loss of a facility.

In select circumstances, a larger customer may be able to have a higher level of local distribution service by providing that customer with another distribution feeder or transformer, but extending the option to the typical customer would become cost prohibitive if individual distribution facilities were to be targeted to individual customers. The same logic applies to the transmission grid. Additionally, trying to distinguish between customers at the transmission level during dynamic conditions where instability occurs would be impossible under many conditions.

If the reliability problem is one of adequacy, that is, insufficient resources, when operating personnel have time to take corrective action, customers willing to pay a higher rate could be given preference when adjustments have to be made to restore the load–generation balance. Individual customers also could arrange for their supplier to maintain additional generating reserves for them at added cost. The process of implementing such a plan could rely on either financial mechanisms or physical mechanisms to disconnect customers not opting for higher levels of reliability.

GENERATION:

Prior to the restructuring of the industry, generating capacity was traditionally installed to meet a statistically determined reserve requirement, that is, an amount of installed capacity over and above the expected peak load obligation of the supplier. The amount of required reserve was related to a probability of loss of load. The precise determination was tailored to each system and reflected its planning and operating philosophies. The determination usually reflected, for each year, statistics on the reliability of its existing individual generators, the expectation of hourly peak loads, the amount of aid available from nearby systems, intra area transmission capabilities, and various levels of remedial actions by operators.

In the evolving industry, the question is unanswered of whether the level of installed generation capacity should be a design requirement or should be market determined. NERC removed from its planning criteria a requirement for a targeted installed reserve, relying instead on a market mechanism to set the installed generation reserve level. A number of regional entities have implemented a required generation reserve obligation. NERC is revisiting the issue.

Another important consideration in the installed generation picture is the diversity of the fuel supply. Consistent with costs, a diverse fuel generation mix supplies an additional level of reliability.

Relying on any one type of fuel, whether hydro, nuclear, coal, oil, solar, or wind can expose the system to common-mode outages. As examples, hydro systems are exposed to the impact of droughts, whereas coal- and oil-fired systems can be impacted by a number of disruptions including worker strikes, disruption in boat deliveries of fuel, and freezing of coal piles in the winter. Solar and wind power can obviously be impacted by weather conditions.

TRANSMISSION:

Transmission systems must be optimized in three dimensions in order to achieve the necessary reliability and minimum costs for electric power. They should be optimized “geographically,” that is, the transmission system must meet the needs of all who are served by the synchronous network, not just the needs of the profits of any one system, any one area, or any one region. Included in geographic optimization, transmission facilities must have a certain degree of physical separation to minimize the potential for common-mode failures. They must be optimized “functionally,” that is the transmission system must meet both generation requirements and the requirements of the distribution systems that they supply. These requirements must be balanced on an overall basis.

Finally, transmission systems must be developed to meet needs over a significant period of time since they cannot be changed once constructed. Transmission systems must be developed to not only meet needs this year, but well into the future. They must be optimized “chronologically.” Transmission systems are aging and rapidly growing less adequate.

The average age for transmission lines, transmission cables, circuit breakers, switch gear, substations, transformers, and other equipment is approaching 30 years, with some key facilities more than 75 years old. Maintenance requires equipment to be taken out of service. Transmission outages on our existing systems can be expected to continue to increase. It is growing increasingly difficult to schedule such outages without taking large reliability risks or incurring large cost penalties due to the inability to deliver low-cost power.

DISTRIBUTION:

Planning and operation of the distribution system is still done according to the standards and practices of individual utilities and reflect local reliability requirements and cost considerations. The robustness of the supply to a congested urban area will be considerably greater than that to a rural farm district. However, oversight of the local utility’s performance is usually exercised by state regulatory authorities.

It is not uncommon for post incident reviews to be held by regulators after significant local outages. In many areas, the use of incentive rates of return reflecting distribution system performance is becoming popular. Utility equipment design practices reflect standards developed by national organizations such as the Institute of Electrical and Electronics Engineers (IEEE).

Comments

Popular posts from this blog

BREAKDOWN VOLTAGE AND DIELECTRIC STRENGTH

An insulator or dielectric is a substance within which there are no mobile electrons necessary for electric conduction. However, when the voltage applied to such an insulator exceeds a certain value, then it breaks down and allows a heavy electric current (much larger than the usual leakage current) to flow through it. If the insulator is a solid medium, it gets punctured or cracked. The disruptive or breakdown voltage of an insulator is the minimum voltage required to break it down. Dielectric strength of an insulator or dielectric medium is given by the maximum potential difference which a unit thickness of the medium can withstand without breaking down. In other words, the dielectric strength is given by the potential gradient necessary to cause breakdown of an insulator. Its unit is volt/meter (V/m) although it is usually expressed in KV/mm. For example, when we say that the dielectric strength of air is 3 KV/mm, then it means that the maximum PD which one mm thickness of ...

EQUIPMENT OF STEAM POWER STATION

A modern steam power station is highly complex and has numerous equipment and auxiliaries. However, the most important constituents of a steam power station are: 1. Steam generating equipment 2. Condenser 3. Prime mover 4. Water treatment plant 5. Electrical equipment. 1. STEAM GENERATING EQUIPMENT: This is an important part of steam power station. It is concerned with the generation of superheated steam and includes such items as boiler, boiler furnace, super heater, economizer, air pre-heater and other heat reclaiming devices. (I) BOILER : A boiler is closed vessel in which water is converted into steam by utilizing the heat of coal combustion. Steam boilers are broadly classified into the following two types: (a) Water tube boilers (b) Fire tube boilers In a water tube boiler, water flows through the tubes and the hot gases of combustion flow over these tubes. On the other hand, in a fire tube boiler, the hot products of combustion pass through the tubes surrounded by water. Wate...

TYPES OF SINGLE PHASE MOTORS

Single phase motors are manufactured in fractional kilowatt range to be operated on single phase supply and for use in numerous applications like ceiling fans, refrigerators, food mixers, hair driers, portable drills, vacuum cleaners, washing machines, sewing machines, electric shavers, office machinery etc. Single phase motors are manufactured in different types to meet the requirements of various applications. Single phase motors are classified on the basis of their construction and starting methods employed. The main types of single phase motors are: (a) Induction motors (b) Synchronous motors (c) Commutator motors The various types of motors under each class are shown as under: Repulsion, repulsion induction and reluctance start motors are not used these days, they have been largely replaced by split phase motors with special capacitors which can be designed to perform equally well as repulsion types. In addition they offer such advantages as lower cost and trouble fr...

Advantages of Per Unit System in Power System Analysis | Electrical Engineering

  Advantages of Per Unit System in Power System Analysis In electrical power engineering, the per unit (p.u.) system is one of the most widely used techniques for analyzing and modeling power systems. It is a method of expressing electrical quantities — such as voltage, current, power, and impedance — as fractions of chosen base values rather than their actual numerical magnitudes. This normalization technique provides a universal language for system calculations, minimizing errors, simplifying transformer modeling, and enabling consistency across multiple voltage levels. Because of these benefits, the per unit system is essential in fault analysis, load flow studies, transformer testing, and short-circuit calculations . ⚡ What is the Per Unit System? The per unit system is defined as: Q u a n t i t y ( p u ) = A c t u a l   V a l u e B a s e   V a l u e Quantity_{(pu)} = \dfrac{Actual \ Value}{Base \ Value} Q u an t i t y ( p u ) ​ = B a se   ...

PRIMARY SECONDARY AND TERTIARY FREQUENCY CONTROL IN POWER SYSTEMS

Primary, Secondary and Tertiary Frequency Control in Power Systems Author: Engr. Aneel Kumar Keywords: frequency control, primary frequency control, automatic generation control (AGC), tertiary control, load-frequency control, grid stability. Frequency control keeps the power grid stable by balancing generation and load. When generation and demand drift apart, system frequency moves away from its nominal value (50 or 60 Hz). Grids rely on three hierarchical control layers — Primary , Secondary (AGC), and Tertiary — to arrest frequency deviation, restore the set-point and optimize generation dispatch. Related: Power System Stability — causes & mitigation Overview of primary, secondary and tertiary frequency control in power systems. ⚡ Primary Frequency Control (Droop Control) Primary control is a fast, local response implemented by generator governors (dro...

ELECTRIC MOTOR PRINCIPLES

The electric motor in its simplest terms is a converter of electrical energy to useful mechanical energy. The electric motor has played a leading role in the high productivity of modern industry, and it is therefore directly responsible for the high standard of living being enjoyed throughout the industrialized world. An electric motor’s principle of operation is based on the fact that a current- carrying conductor, when placed in a magnetic field, will have a force exerted on the conductor proportional to the current flowing in the conductor and to the strength of the magnetic field. In alternating current motors, the windings placed in the laminated stator core produce the magnetic field. The aluminum bars in the laminated rotor core are the current carrying conductors upon which the force acts. The resultant action is the rotary motion of the rotor and shaft, which can then be coupled to various devices to be driven and produce the output. Many types of motors are produced today. Un...

FUEL INJECTION SYSTEM OF DIESEL ENGINE

Fuel injection is a system for mixing fuel with air in an internal combustion engine. A fuel injection system is designed and calibrated specifically for the type of fuel it will handle. Most fuel injection systems are for diesel applications. With the advent of electronic fuel injection (EFI), the diesel gasoline hardware has become similar. EFI’s programmable firmware has permitted common hardware to be used with different fuels. Carburetors were the predominant method used to meter fuel before the widespread use of fuel injection. A variety of injection systems have existed since the earliest usage of the internal combustion engine. The primary difference between carburetors and fuel injection is that fuel injection atomizes the fuel by forcibly pumping it through a small nozzle under high pressure, while a carburetor relies on low pressure created by intake air rushing through it to add the fuel to the air stream. The fuel injector is only a nozzle and a valve: the power to inj...